CASE STUDYProgram management · Behavioral health

No more trips back for more money.

A behavioral health plan was consolidating several claims systems into one platform, a multi-year, $30 million program. Past programs had run over budget, and the team wanted to report schedule and cost with confidence. Digineer put its Program Accelerator in place, and after the first round of planning the team freed up fifteen resources.

15Resources freed after the first planning iteration
$30MMulti-year claims-system consolidation
1 platformReplacing multiple existing claims systems

At a glance

Client
A behavioral health plan
Program
Consolidation of multiple claims systems into a single platform
Scale
A multi-year, $30 million initiative
Engagement
Program management tools and process implementation
Capability
Transformation & Value Management

The situation

A big program with a history to overcome

The plan needed to consolidate its existing claims systems onto a single platform and realize the business benefits of doing so. The management team needed a plan that let it report schedule and budget with confidence, and a clear view of what the program would really cost.

In the past, poorly planned programs had disrupted the organization and led to large cost overruns. This time the management team was determined not to go back to the executive team, again and again, asking for more time and money.

Warning signs

  • Past programs with large cost overruns
  • Repeated requests for more funding
  • No clear view of true program cost
  • Resource needs not yet defined
  • Dependencies between many projects

What we did

Structure the program from day one

Digineer implemented its Program Accelerator, a set of processes and tools built for the functions most large programs need. It structures the program, sets resource needs, manages issues and risks and puts a standard project management framework in place.

A maturity baseline

Digineer baselined the team’s processes and project management maturity against industry best practices.

Changes that fit the team

Working with the management team, Digineer chose the process and tool configuration changes that best matched the team’s maturity and reporting needs, then mentored the team through adoption.

Dashboards to steer by

Dashboard reports let the team monitor and control program performance, with reporting extended as needs grew.

The outcome

Control of schedule, budget and people

Fifteen resources freed

After the first iteration of plans, resource leveling, task consolidation and cross-project allocation freed up fifteen resources.

Accurate cost and progress reports

The team can report expenditures and progress accurately, with budget estimates to completion and resource forecasts.

Confidence at the top

Clear status reporting gave the executive team confidence that the program would deliver its expected business benefits.

Dependencies managed

Inter-project dependencies were managed to protect the program’s schedule and budget.

Program Accelerator

Starting a program you cannot afford to overrun?

Digineer’s Program Accelerator structures a large program from the start, so leaders can see its schedule, cost and resources clearly.

Protect your program budget

Client name withheld for confidentiality.